106873-2621 ZEXEL INJECTION-PUMP ASSEMBLY Calibration Data 1068732621


 

Information injection-pump assembly

ZEXEL 106873-2621 1068732621
106873-2621 INJECTION-PUMP ASSEMBLY
Rating:
51
Buy INJECTION-PUMP ASSEMBLY 106873-2621 zexel genuine, new aftermarket engine parts with delivery

Cross reference number

ZEXEL 106873-2621 1068732621


Zexel num
Bosch num
Firm num
Name
106873-2621 
 
   
INJECTION-PUMP ASSEMBLY

Calibration Data:

Adjustment conditions
Test oil
1404 Test oil
  ISO4113 or {SAEJ967d}
Test oil temperature degC   40 40 45
Nozzle and nozzle holder   105780-8140
Bosch type code   EF8511/9A
Nozzle   105780-0000
Bosch type code   DN12SD12T
Nozzle holder   105780-2080
Bosch type code   EF8511/9
Opening pressure MPa   17.2
Opening pressure kgf/cm2   175
Injection pipe
Outer diameter - inner diameter - length (mm)
mm   8-3-600
Overflow valve   131424-4620
Overflow valve opening pressure kPa   255 221 289
Overflow valve opening pressure kgf/cm2   2.6 2.25 2.95
Tester oil delivery pressure kPa   157 157 157
Tester oil delivery pressure kgf/cm2   1.6 1.6 1.6
Direction of rotation (viewed from drive side)
Right
  R
Injection timing adjustment
Direction of rotation (viewed from drive side)
Right
  R
Injection order   1-2-7-3- 4-5-6-8
Pre-stroke mm   4.4 4.35 4.45
Beginning of injection position
Governor side
  NO.1
Difference between angles 1
Cyl.1-2
deg.   45 44.5 45.5
Difference between angles 2
Cal 1-7
deg.   90 89.5 90.5
Difference between angles 3
Cal 1-3
deg.   135 134.5 135.5
Difference between angles 4
Cal 1-4
deg.   180 179.5 180.5
Difference between angles 5
Cal 1-5
deg.   225 224.5 225.5
Difference between angles 6
Cal 1-6
deg.   270 269.5 270.5
Difference between angles 7
Cal 1-8
deg.   315 314.5 315.5
Injection quantity adjustment
Adjusting point   -
Rack position   10.4
Pump speed r/min   650 650 650
Each cylinder's injection qty mm3/st.   151.5 147 156
Basic   *
Fixing the rack   *
Standard for adjustment of the maximum variation between cylinders   *
Injection quantity adjustment_02
Adjusting point   C
Rack position   5.9+-0.5
Pump speed r/min   225 225 225
Each cylinder's injection qty mm3/st.   18 15.3 20.7
Fixing the rack   *
Standard for adjustment of the maximum variation between cylinders   *
Injection quantity adjustment_03
Adjusting point   A
Rack position   R1(10.4)
Pump speed r/min   650 650 650
Average injection quantity mm3/st.   151.5 150.5 152.5
Basic   *
Fixing the lever   *
Injection quantity adjustment_04
Adjusting point   B
Rack position   R1+0.75
Pump speed r/min   1100 1100 1100
Average injection quantity mm3/st.   161.5 157.5 165.5
Fixing the lever   *
Injection quantity adjustment_05
Adjusting point   E
Rack position   -
Pump speed r/min   100 100 100
Average injection quantity mm3/st.   200 160 240
Fixing the lever   *
Remarks
After startup boost setting
 
Timer adjustment
Pump speed r/min   900--
Advance angle deg.   0 0 0
Remarks
Start
 
Timer adjustment_02
Pump speed r/min   850
Advance angle deg.   0.5
Timer adjustment_03
Pump speed r/min   1100
Advance angle deg.   4.5 4 5
Remarks
Finish
 

Test data Ex:

Governor adjustment

Test data 106873-2621
N:Pump speed R:Rack position (mm) (1)Tolerance for racks not indicated: +-0.05mm. (2)Excess fuel setting for starting: SXL (3)Damper spring setting
----------
SXL=11.3+-0.1mm
----------

Speed control lever angle

Test data 106873-2621
F:Full speed
----------

----------
a=19.5deg+-5deg

0000000901

Test data 106873-2621
F:Full load I:Idle (1)Stopper bolt setting
----------

----------
a=10deg+-5deg b=23.5deg+-3deg

Stop lever angle

Test data 106873-2621
N:Pump normal S:Stop the pump. (1)Drive side (2)Use the hole at R = aa (3)Rack position bb (4)Stopper bolt setting
----------
aa=36mm bb=3.7-0.5mm
----------
a=10.5deg+-5deg b=57deg+7deg-5deg

0000001501 MICRO SWITCH

Adjustment of the micro-switch Adjust the bolt to obtain the following lever position when the micro-switch is ON. (1)Speed N1 (2)Rack position Ra
----------
N1=325r/min Ra=5.4+-0.1mm
----------

0000001601 GOVERNOR TORQUE CONTROL

Test data 106873-2621
Dr:Torque control stroke (A): Without torque control spring capsule 1. Adjustment procedures (1)Procedure is the same as that for the RFD (former type), except that the positive torque control stroke must be determined at the full lever setting. 2. Procedures for adjustment (1)Remove the torque control spring capsule. (2)Operate the pump at approximately N1. (End of idling spring operation < N1.) (3)Tilt the lever to the full side. (4)Set so that R = RF. (5)Increase the speed by pushing in the screw (attached to the bracket on the rear of the tension lever) through the adjusting window. (6)Adjust so that the torque control stroke Dr1 can be obtained. (7)Align N2 and N3 with the torque control spring capsule. 3. Final confirmation (1)After final confirmation, temporarily set the load lever to N = N1, R = idling position. (2)From this condition, increase speed to N = N4. (3)Confirm that positive torque control stroke is Dr2.
----------
N1=500r/min N2=- N3=- N4=1100r/min RF=R1(10.4)mm Dr1=0.75mm Dr2=0+0.3mm
----------

Timing setting

Test data 106873-2621
(1)Pump vertical direction (2)Coupling's key groove position at No 1 cylinder's beginning of injection (3)B.T.D.C.: aa (4)-
----------
aa=12deg
----------
a=(40deg)




Information:


Typical Example1. Loosen two bolts (2) and two nuts (3). Remove bolt (1), and remove fan drive belts (4).
Typical Example2. Remove the nuts and bolts that hold the fan drive in place. Remove fan drive (5). The following steps are for installation of the fan drive.3. Put fan drive (5) in position on the timing gear cover.4. Install bolts (2) and nuts (3) loosely. Make a replacement of the belts as a set only.5. Install fan belts (4). Install bolt (1). Make an adjustment to the belt tension with tool (A). Measure the belt farthest away from the engine. Tighten new belts to a gauge indication of 120 5. After the engine is operated at high idle for a minimum of 30 minutes, make another adjustment to the belt tension. The correct tension for used belts is a gauge indication of 90 10.6. Tighten bolts (2) and nuts (3) that hold the fan drive in place.Disassemble Fan Drive
Start By:a. remove fan drive 1. Remove two bolts (2) that hold the fan adapter to the pulley.2. Remove fan adapter (1) from the pulley 3. Remove bolts (3) and washer (4). Remove seal (5). 4. Remove pulley (8) from bracket (6).5. Remove bearing (10) and spacer (9) from the pulley. Remove spacer (7), seal (11) and bearing (12) from the pulley.Assemble Fan Drive
1. Install bearing (12) in the rear of pulley (8). 2. Install lip-type seal (11) with tooling (A). The lip of the seal must be away from the bearing. Put 5P960 Multipurpose Type Grease on the lip of the seal.3. Install spacer (7) so the end with the taper is toward the inside of pulley (8).4. Install spacer (9) and bearing (4) in the front of the pulley. 5. Put seal (5) on the front of the pulley. Install the pulley on bracket (6). 6. Install washer (4) and bolts (3) that hold the pulley in position.7. Install the fan drive adapter on the pulley.8. Fill the fan drive with 5P960 Multipurpose Type Grease.End By:a. install fan drive

Have questions with 106873-2621?





Group cross 106873-2621 ZEXEL

 
 
INJECTION-PUMP ASSEMBLY
106873-2621  
 
 
INJECTION-PUMP ASSEMBLY
 
 
INJECTION-PUMP ASSEMBLY
 
 
INJECTION-PUMP ASSEMBLY
 
 
INJECTION-PUMP ASSEMBLY

Mitsubishi 

9 400 618 370 
ME160500 
INJECTION-PUMP ASSEMBLY
8M20-I