Information injection-pump assembly
ZEXEL
106871-5330
1068715330

Rating:
Cross reference number
ZEXEL
106871-5330
1068715330
Zexel num
Bosch num
Firm num
Name
106871-5330
INJECTION-PUMP ASSEMBLY
Calibration Data:
Adjustment conditions
Test oil
1404 Test oil ISO4113 or {SAEJ967d}
1404 Test oil ISO4113 or {SAEJ967d}
Test oil temperature
degC
40
40
45
Nozzle and nozzle holder
105780-8140
Bosch type code
EF8511/9A
Nozzle
105780-0000
Bosch type code
DN12SD12T
Nozzle holder
105780-2080
Bosch type code
EF8511/9
Opening pressure
MPa
17.2
Opening pressure
kgf/cm2
175
Injection pipe
Outer diameter - inner diameter - length (mm) mm 8-3-600
Outer diameter - inner diameter - length (mm) mm 8-3-600
Overflow valve
132424-0620
Overflow valve opening pressure
kPa
157
123
191
Overflow valve opening pressure
kgf/cm2
1.6
1.25
1.95
Tester oil delivery pressure
kPa
157
157
157
Tester oil delivery pressure
kgf/cm2
1.6
1.6
1.6
Direction of rotation (viewed from drive side)
Right R
Right R
Injection timing adjustment
Direction of rotation (viewed from drive side)
Right R
Right R
Injection order
1-8-7-5-
4-3-6-2
Pre-stroke
mm
3.65
3.6
3.7
Beginning of injection position
Governor side NO.1
Governor side NO.1
Difference between angles 1
Cal 1-8 deg. 45 44.5 45.5
Cal 1-8 deg. 45 44.5 45.5
Difference between angles 2
Cal 1-7 deg. 90 89.5 90.5
Cal 1-7 deg. 90 89.5 90.5
Difference between angles 3
Cal 1-5 deg. 135 134.5 135.5
Cal 1-5 deg. 135 134.5 135.5
Difference between angles 4
Cal 1-4 deg. 180 179.5 180.5
Cal 1-4 deg. 180 179.5 180.5
Difference between angles 5
Cal 1-3 deg. 225 224.5 225.5
Cal 1-3 deg. 225 224.5 225.5
Difference between angles 6
Cal 1-6 deg. 270 269.5 270.5
Cal 1-6 deg. 270 269.5 270.5
Difference between angles 7
Cyl.1-2 deg. 315 314.5 315.5
Cyl.1-2 deg. 315 314.5 315.5
Injection quantity adjustment
Adjusting point
A
Rack position
10
Pump speed
r/min
700
700
700
Average injection quantity
mm3/st.
123
122
124
Max. variation between cylinders
%
0
-4
4
Basic
*
Fixing the lever
*
Injection quantity adjustment_02
Adjusting point
C
Rack position
6.9+-0.5
Pump speed
r/min
280
280
280
Average injection quantity
mm3/st.
11.5
9.5
13.5
Max. variation between cylinders
%
0
-10
10
Fixing the rack
*
Injection quantity adjustment_03
Adjusting point
D
Rack position
-
Pump speed
r/min
100
100
100
Average injection quantity
mm3/st.
145
125
165
Fixing the lever
*
Remarks
After startup boost setting
After startup boost setting
Timer adjustment
Pump speed
r/min
550--
Advance angle
deg.
0
0
0
Remarks
Start
Start
Timer adjustment_02
Pump speed
r/min
500
Advance angle
deg.
0.5
Timer adjustment_03
Pump speed
r/min
1100
Advance angle
deg.
3.5
3
4
Remarks
Finish
Finish
Test data Ex:
Governor adjustment

N:Pump speed
R:Rack position (mm)
(1)Tolerance for racks not indicated: +-0.05mm.
(2)Excess fuel setting for starting: SXL (N = N1)
(3)Damper spring setting
(4)Variable speed specification: idling adjustment
(5)Fix the lever at the full-load position at delivery.
(6)Main spring setting
----------
SXL=10.2+-0.1mm N1=400r/min
----------
----------
SXL=10.2+-0.1mm N1=400r/min
----------
Speed control lever angle

F:Full speed
I:Idle
(1)Pump speed = aa
(2)Set the stopper bolt (fixed at full-load position at delivery.)
----------
aa=290r/min
----------
a=13.5deg+-5deg b=5.5deg+-5deg
----------
aa=290r/min
----------
a=13.5deg+-5deg b=5.5deg+-5deg
0000000901

F:Full load
I:Idle
(1)Stopper bolt setting
(2)Use the hole at R = aa
----------
aa=46mm
----------
a=25deg+-3deg b=33deg+-5deg
----------
aa=46mm
----------
a=25deg+-3deg b=33deg+-5deg
Stop lever angle

N:Pump normal
S:Stop the pump.
(1)Drive side
----------
----------
a=20deg+-5deg b=64deg+-5deg
----------
----------
a=20deg+-5deg b=64deg+-5deg
Timing setting

(1)Pump vertical direction
(2)Position of the coupling's key groove at the beginning of injection of the No. 8 cylinder.
(3)-
(4)-
----------
----------
a=(90deg)
----------
----------
a=(90deg)
Information:
Illustration 9 g06426461
(1) For 323, 330, and 330GC machines use 580-1893 Plate As / For 336GC machines use 581-5268 Plate As
(Q) Bolt and washer
(R) Plate
Install plate assembly (1) using plate (R), bolt, and washer (Q). Tighten the bolts to 55 10 N m (41 7 lb ft). Refer to Illustration 9.
Illustration 10 g06426462
(7) 365-0162 Special Connector
(F) Injector
Install special connector (7) to injector (F). Refer to Illustration 10.
Illustration 11 g06426463
(2) 573-8722 Tank
(8) 3S-2093 Cable Strap
(E) Hose
(M) Harness
Connect hose (E) to tank (2). Refer to Illustration 11.
Illustration 12 g06426465
View of area T
(1) For 323, 330, and 330GC machines use 580-1893 Plate As / For 336GC machines use 581-5268 Plate As
(P) Clip
(S) Bolt and washer
(D1) 45 Degree
Install clip (P) using bolt and washer (S), torque to 28 7 N m (248 62 lb in). Refer to Illustration 12.
Secure the harness (M) using cable strap (8). After tie up, cut all the surplus of strap. Refer to Illustration 11.
Reinstall upper cover (A) and close the upper cover (B). Refer to Illustration 1 and Illustration 2.Replacement Procedure for 336 Excavators
Do not operate or work on this product unless you have read and understood the instruction and warnings in the relevant Operation and Maintenance Manuals and relevant service literature. Failure to follow the instructions or heed the warnings could result in injury or death. Proper care is your responsibility.
Table 3
Required Parts
Item Qty Part Number Part Name
1 1 471-9926 Tank
2 1 581-3324 Plate As
3 1 327-0325 Cable Strap
Illustration 13 g06426466
(A) Upper cover
(B) Upper cover
Remove the upper cover (A) and open the upper cover (B). Refer to Illustration 13.
Illustration 14 g06426467
(C) Tank assembly
(E) Hose
(F) Hose
(G) Strap
Disconnect hose (E) and hose (F) from tank assembly (C). Cut and remove the strap (G). Refer to Illustration 14.
Illustration 15 g06426468
(C) Tank assembly
(H) Bolt and washer
(J) Bolt and washer
(K) Plate assembly
Remove tank assembly (C) by loosening the bolt and washer (H). Refer to Illustration 15.
Remove plate assembly (K) by loosening the bolt and washer (J). Refer to Illustration 15.
Illustration 16 g06426469
(F) Hose
(D1) 10.0 mm (0.4 inch)
Cut and remove the end of hose (F) by 10.0 mm (0.4 inch). Refer to Illustration 16.
Illustration 17 g06426470
(1) 471-9926 Tank
(2) 581-3324 Plate As
(3) 327-0325 Cable Strap
(E) Hose
(H) Bolt and washer
(J) Bolt and washer
(F) Hose
Install the plate assembly (2) and tank (1) using bolt and washer (J) and bolt and washer (H). Refer to Illustration 17.
Connect hose (E) and hose (F) to tank (1). Add cable strap (3) to secure hose. After tie up, cut all the surplus of strap. Refer to Illustration 17.
Reinstall upper cover (A) and close the upper cover (B). Refer to Illustration 13.
Have questions with 106871-5330?
Group cross 106871-5330 ZEXEL
Nissan-Diesel
Nissan-Diesel
106871-5330
INJECTION-PUMP ASSEMBLY