106682-9400 ZEXEL INJECTION-PUMP ASSEMBLY Calibration Data 1066829400 6162752130


 

Information injection-pump assembly

ZEXEL 106682-9400 1066829400
KOMATSU 6162752130 6162752130
106682-9400 INJECTION-PUMP ASSEMBLY
Rating:
30
Buy INJECTION-PUMP ASSEMBLY 106682-9400 zexel genuine, new aftermarket engine parts with delivery

Service parts 106682-9400 INJECTION-PUMP ASSEMBLY:

1. _
2. FUEL INJECTION PUMP 106068-2890
3. GOVERNOR 105447-1740
4. SUPPLY PUMP 105237-1541
5. AUTOM. ADVANCE MECHANIS
6. COUPLING PLATE 105664-0390
7. COUPLING PLATE
8. _
9. _
10. NOZZLE AND HOLDER ASSY 105111-4640
11. Nozzle and Holder 6162-15-3100
12. Open Pre:MPa(Kqf/cm2) 26.0{265}
13. NOZZLE-HOLDER 105041-7140
14. NOZZLE 105025-0870
15. NOZZLE SET

Include in #1:

106682-9400 as INJECTION-PUMP ASSEMBLY

Cross reference number

ZEXEL 106682-9400 1066829400
KOMATSU 6162752130 6162752130


Zexel num
Bosch num
Firm num
Name
106682-9400 
106682-9401 
 
6162752130  KOMATSU
INJECTION-PUMP ASSEMBLY
SA6D170 * K

Calibration Data:

Adjustment conditions
Test oil
1404 Test oil
  ISO4113 or {SAEJ967d}
Test oil temperature degC   40 40 45
Nozzle and nozzle holder   105780-8130
Bosch type code   EFEP215A
Nozzle   105780-0050
Bosch type code   DN6TD119NP1T
Nozzle holder   105780-2090
Bosch type code   EFEP215
Opening pressure MPa   17.2
Opening pressure kgf/cm2   175
Injection pipe
Outer diameter - inner diameter - length (mm)
mm   8-4-1000
Overflow valve   131425-1320
Overflow valve opening pressure kPa   255 221 289
Overflow valve opening pressure kgf/cm2   2.6 2.25 2.95
Tester oil delivery pressure kPa   157 157 157
Tester oil delivery pressure kgf/cm2   1.6 1.6 1.6
Direction of rotation (viewed from drive side)
Left
  L
Injection timing adjustment
Direction of rotation (viewed from drive side)
Left
  L
Injection order   1-5-3-6- 2-4
Pre-stroke mm   2.8 2.75 2.85
Beginning of injection position
Drive side
  NO.1
Difference between angles 1
Cal 1-5
deg.   60 59.5 60.5
Difference between angles 2
Cal 1-3
deg.   120 119.5 120.5
Difference between angles 3
Cal 1-6
deg.   180 179.5 180.5
Difference between angles 4
Cyl.1-2
deg.   240 239.5 240.5
Difference between angles 5
Cal 1-4
deg.   300 299.5 300.5
Injection quantity adjustment
Adjusting point   A
Rack position   13.9
Pump speed r/min   850 850 850
Average injection quantity mm3/st.   492 487 497
Max. variation between cylinders %   0 -3 3
Basic   *
Fixing the lever   *
Boost pressure kPa   62 62
Boost pressure mmHg   465 465
Injection quantity adjustment_02
Adjusting point   C
Rack position   6.9+-0.5
Pump speed r/min   335 335 335
Average injection quantity mm3/st.   12.5 7.5 17.5
Max. variation between cylinders %   0 -15 15
Fixing the rack   *
Boost pressure kPa   0 0 0
Boost pressure mmHg   0 0 0
Boost compensator adjustment
Pump speed r/min   600 600 600
Rack position   R1-2.2
Boost pressure kPa   17.3 14.6 20
Boost pressure mmHg   130 110 150
Boost compensator adjustment_02
Pump speed r/min   600 600 600
Rack position   R1(14.4)
Boost pressure kPa   48.7 42 55.4
Boost pressure mmHg   365 315 415

Test data Ex:

Governor adjustment

Test data 106682-9400
N:Pump speed R:Rack position (mm) (1)Target notch: K (2)Boost compensator stroke: BCL (3)Rack difference between N = N1 and N = N2
----------
K=20 BCL=2.2+-0.1mm N1=850r/min N2=650r/min
----------

Speed control lever angle

Test data 106682-9400
F:Full speed I:Idle S:Stop (1)Use the hole at R = aa
----------
aa=90mm
----------
a=(17deg)+-5deg b=(25deg)+-5deg c=52deg+-3deg

0000001501 LEVER

Test data 106682-9400
1. Adjustment of the control lever (1)Perform idling with the speed lever (a) contacting the pushrod (b) At this time, confirm that the spring (c) is not compressed by speed lever (a)'s operating torque. (2)To set the stop position, compress spring (c) using the speed lever (a) and adjust the rack so that it contacts the guide screw at position L1. Then, set and fix using the lock nut (e). Adjust rack position at this time using shim (f). (3)After pulling the speed lever (a) in the stop direction and releasing it, confirm that it returns to the idle position.
----------
L1=0.2~2mm
----------

Timing setting

Test data 106682-9400
(1)Pump vertical direction (2)Coupling's key groove position at No 1 cylinder's beginning of injection (3)- (4)-
----------

----------
a=(40deg)




Information:

Start By:a. remove valve covers 1. Use tooling (A), and disconnect fuel line (1) at each end. Remove the fuel line from the engine. 2. Use tool (B), and remove retainer (2) from the adapter.3. Remove the fuel injection nozzles with tooling (C) as follows:a. Install the 6V6983 Adapter and the 8T3199 Screw into nozzle assembly (3).b. Install the 8T3198 Tube over the 8T3199 Screw.c. Use the 1B4206 Nut on the 8T3199 Screw.d. Use the 1B4206 Nut on the 8T3199 Screw to pull the fuel injection nozzle from the adapter.4. Remove compression seal (4) and carbon dam seal (8) from fuel injection nozzle (3).5. Use tool (D), and remove adapter (6) from the cylinder head.6. Remove gasket (7) and seal (5) from adapter (6). The following steps are for installation of the fuel injection nozzles and adapters.7. Use tool (E) to clean the bore in adapter (6). Use an open end wrench or tap driver to turn tool (E).8. Inspect seal (5) for damage or wear. Replace the seal if necessary.9. Put washer (7) and seal (5) in position on adapter (6).10. Put liquid soap in the bores of the cylinder head and on seals (5) in the adapters.11. Put 5P3931 Anti-Seize Compound on the threads of adapter (6), and install the adapter in the cylinder head assembly.12. Use tool (D), and tighten the adapter to a torque of 205 14 N m (150 10 lb.ft.).
Make sure the correct compression seal washer (4) is used when the nozzle assembly is installed in the adapter. Only copper washers are to be used with this adapter.
13. Install compression seal washer (4), and use tool (F) to install carbon dam seal (8) on the fuel injection nozzle.14. Put fuel injection nozzle (3) in position in the adapter, and install retainer (2).15. Use tool (B) to tighten retainer (2) to a torque of 48 7 N m (35 5 lb.ft.).16. Install fuel line (1). Tighten the nuts on the fuel line with tooling (A) to a torque of 40 7 N m (30 5 lb.ft.).End By:a. install valve covers

Have questions with 106682-9400?





Group cross 106682-9400 ZEXEL

Komatsu 

106682-9400  

106682-9401 
 
6162752130 
INJECTION-PUMP ASSEMBLY
SA6D170
 
 
INJECTION-PUMP ASSEMBLY
 
 
INJECTION-PUMP ASSEMBLY

Komatsu 

9 400 617 617 
6162752131 
INJECTION-PUMP ASSEMBLY
SA6D170
 
6162752220 
INJECTION-PUMP ASSEMBLY
SA6D170
 
 
INJECTION-PUMP ASSEMBLY
 
 
INJECTION-PUMP ASSEMBLY
 
 
INJECTION-PUMP ASSEMBLY

Komatsu 

9 400 611 343 
6162752221 
INJECTION-PUMP ASSEMBLY
SA6D170
 
6212721420 
INJECTION-PUMP ASSEMBLY
SAA6D140
 
 
INJECTION-PUMP ASSEMBLY
 
 
INJECTION-PUMP ASSEMBLY
9 400 611 539 
 
INJECTION-PUMP ASSEMBLY

Komatsu 

9 400 617 618 
6212721421 
INJECTION-PUMP ASSEMBLY
SAA6D140
9 400 612 129 
6162752230 
INJECTION-PUMP ASSEMBLY
S6D170
 
 
INJECTION-PUMP ASSEMBLY
 
 
INJECTION-PUMP ASSEMBLY
 
 
INJECTION-PUMP ASSEMBLY

Komatsu 

9 400 612 381 
6162752120 
INJECTION-PUMP ASSEMBLY
SA6D170
 
6152721970 
INJECTION-PUMP ASSEMBLY
SAA6D125
9 400 610 979 
6152721971 
INJECTION-PUMP ASSEMBLY
SAA6D125
F 019 Z10 203 
6152721980 
INJECTION-PUMP ASSEMBLY
SAA6D125
9 400 617 619 
6152721981 
INJECTION-PUMP ASSEMBLY
SAA6D125
 
 
INJECTION-PUMP ASSEMBLY

Komatsu 

9 400 611 668 
6215711850 
INJECTION-PUMP ASSEMBLY
SA12V140
 
 
INJECTION-PUMP ASSEMBLY
SA12V140
 
 
INJECTION-PUMP ASSEMBLY

Komatsu 

9 400 617 620 
6215711851 
INJECTION-PUMP ASSEMBLY
SA12V140
9 400 611 845 
6162751950 
INJECTION-PUMP ASSEMBLY
SA6D170
 
 
INJECTION-PUMP ASSEMBLY

Komatsu 

9 400 617 621 
6215711290 
INJECTION-PUMP ASSEMBLY
SA12V140
Back to top