101603-9081 ZEXEL INJECTION-PUMP ASSEMBLY Calibration Data 1016039081


 

Information injection-pump assembly

ZEXEL 101603-9081 1016039081
101603-9081 INJECTION-PUMP ASSEMBLY
Rating:
65
Buy INJECTION-PUMP ASSEMBLY 101603-9081 zexel genuine, new aftermarket engine parts with delivery

Cross reference number

ZEXEL 101603-9081 1016039081


Zexel num
Bosch num
Firm num
Name
101603-9081 
101603-9084 
 
  NISSAN-DIESEL
INJECTION-PUMP ASSEMBLY
FE6A *

Calibration Data:

Adjustment conditions
Test oil
1404 Test oil
  ISO4113 or {SAEJ967d}
Test oil temperature degC   40 40 45
Nozzle and nozzle holder   105780-8140
Bosch type code   EF8511/9A
Nozzle   105780-0000
Bosch type code   DN12SD12T
Nozzle holder   105780-2080
Bosch type code   EF8511/9
Opening pressure MPa   17.2
Opening pressure kgf/cm2   175
Injection pipe
Outer diameter - inner diameter - length (mm)
mm   6-2-600
Overflow valve opening pressure kPa   157 123 191
Overflow valve opening pressure kgf/cm2   1.6 1.25 1.95
Tester oil delivery pressure kPa   157 157 157
Tester oil delivery pressure kgf/cm2   1.6 1.6 1.6
Direction of rotation (viewed from drive side)
Right
  R
Injection timing adjustment
Direction of rotation (viewed from drive side)
Right
  R
Injection order   1-4-2-6- 3-5
Pre-stroke mm   3 2.95 3.05
Beginning of injection position
Drive side
  NO.1
Difference between angles 1
Cal 1-4
deg.   60 59.5 60.5
Difference between angles 2
Cyl.1-2
deg.   120 119.5 120.5
Difference between angles 3
Cal 1-6
deg.   180 179.5 180.5
Difference between angles 4
Cal 1-3
deg.   240 239.5 240.5
Difference between angles 5
Cal 1-5
deg.   300 299.5 300.5
Injection quantity adjustment
Adjusting point   -
Rack position   11.3
Pump speed r/min   600 600 600
Average injection quantity mm3/st.   48.2 46.6 49.8
Max. variation between cylinders %   0 -3.5 3.5
Basic   *
Fixing the rack   *
Standard for adjustment of the maximum variation between cylinders   *
Injection quantity adjustment_02
Adjusting point   -
Rack position   9.8+-0.5
Pump speed r/min   300 300 300
Average injection quantity mm3/st.   9 7.2 10.8
Max. variation between cylinders %   0 -10 10
Fixing the rack   *
Standard for adjustment of the maximum variation between cylinders   *
Remarks
Adjust only variation between cylinders; adjust governor according to governor specifications.
 
Injection quantity adjustment_03
Adjusting point   A
Rack position   R1(11.3)
Pump speed r/min   600 600 600
Average injection quantity mm3/st.   48.2 47.2 49.2
Basic   *
Fixing the lever   *
Injection quantity adjustment_04
Adjusting point   B
Rack position   R1-0.2
Pump speed r/min   1000 1000 1000
Average injection quantity mm3/st.   63.6 60.4 66.8
Fixing the lever   *
Injection quantity adjustment_05
Adjusting point   I
Rack position   14.3+-0. 5
Pump speed r/min   100 100 100
Average injection quantity mm3/st.   80 80 90
Fixing the lever   *
Rack limit   *
Timer adjustment
Pump speed r/min   (1140)
Advance angle deg.   0 0 0
Remarks
Start
 
Timer adjustment_02
Pump speed r/min   1500
Advance angle deg.   4 3.5 4.5
Remarks
Finish
 

Test data Ex:

Governor adjustment

Test data 101603-9081
N:Pump speed R:Rack position (mm) (1)Torque cam stamping: T1 (2)RACK LIMIT
----------
T1=C42
----------

Speed control lever angle

Test data 101603-9081
F:Full speed I:Idle (1)Stopper bolt set position 'H'
----------

----------
a=26.5deg+-5deg b=40deg+-3deg

Stop lever angle

Test data 101603-9081
N:Pump normal S:Stop the pump.
----------

----------
a=20deg+-5deg b=40deg+-5deg

Timing setting

Test data 101603-9081
(1)Pump vertical direction (2)Position of timer's threaded hole at No 1 cylinder's beginning of injection (3)- (4)-
----------

----------
a=(60deg)




Information:


Illustration 13 g02915447
Plugged DOC
The DOC utilizes a “pass-through” technology, which is different from the “wall flow” design of a DPF. When a light is shined through the DOC, a visible light should be able to pass through. Utilize a flashlight to check for a plugged DOC face. Aim the flashlight into the DOC inlet, visible light should be seen through the DOC. A plugged DOC can be caused by high oil consumption, not recommended fuel additives, or wrong engine oil types. Refer to the Operation and Maintenance Manual for recommended fluids to use. If light cannot be seen on the outlet of the DOC, then replace the DOC.CRS Bodies
Illustration 14 g06342815
Combustion Group
(1) Head Group - Combustion
(2) Gasket
(3) Tube
(4) Body Assembly - Exhaust CombustionCRS Combustion Body (4) contains the flame necessary for CRS Regeneration. There are two combustion stages that occur within the CRS Body: the primary and secondary combustion. The primary combustion of air and fuel occur within Tube (3) to create the CRS flame immediately following Head Group (1). The secondary combustion of the CRS flame and exhaust gas from the turbocharger occur within Body Assembly (4).The body assembly is the only salvageable part of the combustion group. The body assembly must be cleaned, inspected, and pressure tested prior to reuse.Cleaning
Start by isolating the CRS body from all other CRS exhaust components. Remove the head group, the mounting studs, the tube, and the two gaskets.The gasket area and the bellows joints are the two areas of the CRS body that must be cleaned thoroughly to make a proper seal.Cleaning the remainder of the CRS body is not required. If cleaning the CRS body is desired, then first perform the visual inspection, vacuum inspection, and welding procedures prior to washing the CRS body. This step is to ensure that the CRS body is salvageable, not cracked, and to keep water from getting trapped behind the heat shield.If washing is preferred, then use soap and water as a cleaning solution. Do not submerge the CRS body to prevent water from becoming trapped between the heat shield and the CRS body. A cylinder washing brush, a wire brush with handle, and a greenScotch Brite pads are all acceptable cleaning equipment. Removal of all diesel particulates is not required for inspection.
Do not use any combustible solvents to clean the CRS body.
Visual Inspection
A visual inspection of the CRS body must be completed, special equipment or crack detecting solution is not required. Visually inspect the exterior of the CRS body. Small cracks and/or punctures found on the stainless steel heat shield is normal and should be expected. Inspect the bellows sealing joints and the CRS head mating surface for visual damage.Light surface rust is typically not a problem unless rust is found on a bellows joint or the CRS gasket mating surface. Light rust in these two areas must be removed using a Scotch Brite pad.Serviceability
All bolts, studs, and clamps are not reusable and must be replaced with new components.Any thread damage in the mounting

Have questions with 101603-9081?





Group cross 101603-9081 ZEXEL

 
 
INJECTION-PUMP ASSEMBLY
6D22

Dpico 

 
 
INJECTION-PUMP ASSEMBLY
6D22

Nissan-Diesel 

 
 
INJECTION-PUMP ASSEMBLY
NE6
9 400 615 285 
1671395076 
INJECTION-PUMP ASSEMBLY
NE6
9 400 615 286 
 
INJECTION-PUMP ASSEMBLY
6D16

Nissan-Diesel 

 
 
INJECTION-PUMP ASSEMBLY
FE6B
 
 
INJECTION-PUMP ASSEMBLY
FE6B
 
 
INJECTION-PUMP ASSEMBLY

Nissan-Diesel 

 
16713Z6103 
INJECTION-PUMP ASSEMBLY
FE6B
 
1671395100 
INJECTION-PUMP ASSEMBLY
NE6
9 400 615 287 
1671395101 
INJECTION-PUMP ASSEMBLY
NE603
 
 
INJECTION-PUMP ASSEMBLY
FE6B
 
 
INJECTION-PUMP ASSEMBLY

Nissan-Diesel 

9 400 619 533 
16700Z5667 
INJECTION-PUMP ASSEMBLY
FE6B
9 400 615 288 
16700Z5706 
INJECTION-PUMP ASSEMBLY
FE6B
 
16700Z5668 
INJECTION-PUMP ASSEMBLY
FE6B
101603-9081  

101603-9084 
 
 
INJECTION-PUMP ASSEMBLY
FE6A
 
16713Z5673 
INJECTION-PUMP ASSEMBLY
FE6A
 
 
INJECTION-PUMP ASSEMBLY
FE6B
 
16713Z5674 
INJECTION-PUMP ASSEMBLY
FE6B
Back to top