101402-4160 ZEXEL INJECTION-PUMP ASSEMBLY Calibration Data 1014024160 8970200410


 

Information injection-pump assembly

ZEXEL 101402-4160 1014024160
ISUZU 8970200410 8970200410
101402-4160 INJECTION-PUMP ASSEMBLY
Rating:
54
Buy INJECTION-PUMP ASSEMBLY 101402-4160 zexel genuine, new aftermarket engine parts with delivery

Service parts 101402-4160 INJECTION-PUMP ASSEMBLY:

1. _
2. FUEL INJECTION PUMP 101040-8900
3. GOVERNOR 105411-1560
4. SUPPLY PUMP 105220-6000
5. AUTOM. ADVANCE MECHANIS
6. COUPLING PLATE
7. COUPLING PLATE 156637-2320
8. _
9. _
10. NOZZLE AND HOLDER ASSY 105100-6241
11. Nozzle and Holder 1-15300-142-1
12. Open Pre:MPa(Kqf/cm2) 18.1{185}
13. NOZZLE-HOLDER 105030-3201
14. NOZZLE 105015-5860
15. NOZZLE SET

Include in #1:

101402-4160 as INJECTION-PUMP ASSEMBLY

Cross reference number

ZEXEL 101402-4160 1014024160
ISUZU 8970200410 8970200410


Zexel num
Bosch num
Firm num
Name
101402-4160 
101402-4161 
 
8970200410  ISUZU
INJECTION-PUMP ASSEMBLY
4BG1 * K

Calibration Data:

Adjustment conditions
Test oil
1404 Test oil
  ISO4113 or {SAEJ967d}
Test oil temperature degC   40 40 45
Nozzle and nozzle holder   105780-8140
Bosch type code   EF8511/9A
Nozzle   105780-0000
Bosch type code   DN12SD12T
Nozzle holder   105780-2080
Bosch type code   EF8511/9
Opening pressure MPa   17.2
Opening pressure kgf/cm2   175
Injection pipe
Outer diameter - inner diameter - length (mm)
mm   6-2-600
Overflow valve   131424-4920
Overflow valve opening pressure kPa   127 107 147
Overflow valve opening pressure kgf/cm2   1.3 1.1 1.5
Tester oil delivery pressure kPa   157 157 157
Tester oil delivery pressure kgf/cm2   1.6 1.6 1.6
Direction of rotation (viewed from drive side)
Right
  R
Injection timing adjustment
Direction of rotation (viewed from drive side)
Right
  R
Injection order   1-3-4-2
Pre-stroke mm   3.6 3.55 3.65
Beginning of injection position
Drive side
  NO.1
Difference between angles 1
Cal 1-3
deg.   90 89.5 90.5
Difference between angles 2
Cal 1-4
deg.   180 179.5 180.5
Difference between angles 3
Cyl.1-2
deg.   270 269.5 270.5
Injection quantity adjustment
Adjusting point   A
Rack position   10.6
Pump speed r/min   1400 1400 1400
Average injection quantity mm3/st.   159.2 157.6 160.8
Max. variation between cylinders %   0 -2.5 2.5
Basic   *
Fixing the lever   *
Boost pressure kPa   106.6 106.6
Boost pressure mmHg   800 800
Injection quantity adjustment_02
Adjusting point   B
Rack position   5.9+-0.5
Pump speed r/min   275 275 275
Average injection quantity mm3/st.   17.3 16 18.6
Max. variation between cylinders %   0 -14 14
Fixing the rack   *
Boost pressure kPa   0 0 0
Boost pressure mmHg   0 0 0
Boost compensator adjustment
Pump speed r/min   550 550 550
Rack position   8.4
Boost pressure kPa   20 17.3 22.7
Boost pressure mmHg   150 130 170
Boost compensator adjustment_02
Pump speed r/min   550 550 550
Rack position   (10.6)
Boost pressure kPa   93.3 86.6 100
Boost pressure mmHg   700 650 750

Test data Ex:

Governor adjustment

Test data 101402-4160
N:Pump speed R:Rack position (mm) (1)Target notch: K (2)Set idle sub-spring (3)Main spring setting (4)Boost compensator stroke
----------
K=12
----------

Speed control lever angle

Test data 101402-4160
F:Full speed I:Idle (1)Stopper bolt setting
----------

----------
a=12deg+-5deg b=26deg+-5deg

Stop lever angle

Test data 101402-4160
N:Pump normal S:Stop the pump. (1)Speed = aa, rack position = bb (sealed at shipping)
----------
aa=0r/min bb=1-0.2mm
----------
a=32deg+-5deg b=(55deg)

Timing setting

Test data 101402-4160
(1)Pump vertical direction (2)Position of gear mark 'CC' at No 1 cylinder's beginning of injection (3)B.T.D.C.: aa (4)-
----------
aa=12deg
----------
a=(90deg)




Information:

start by:a) remove timing gear cover1. Remove the turbocharger return tube from the flywheel housing. 2. Remove two studs (1).3. Turn the engine with tool (A) to remove four bolts (2) from the rear balance weight gear.4. Turn the engine again with tool (A) until the "V" marks on all the timing gears are in alignment with each other.5. With the timing marks in alignment, install tooling (B) in the location of rear studs (1). Make sure the bolts [tooling (B)] are in the rear balance weight gear. Tighten the bolts [tooling (B)] evenly until the rear balance weight gear is free of the camshaft. 6. Remove bolts (3) and thrust plate (4). Pull the camshaft forward as far as possible [approximately 1/4 in. (6.4 mm)]. 7. Remove four bolts (6) and plate (7).8. Remove bolts (5) and the thrust plates that hold balance gear (8) in position. The gear must be pulled forward as bolts (5) are removed.9. After bolts (5) are all removed, remove balance gear (8). If balance gear (8) can not be removed turn the engine a small amount with tool (A) until the gear is free.10. Remove the bearing from balance gear (8) with tooling (D) and an arbor press. 11. Remove crankshaft gear (9) with tool (C).Install Timing Gears
1. Install the bearing in the front balance gear with tooling (A) and an arbor press. The bearing joint must be on a center line of the balance gear with in 20°.2. Heat crankshaft gear (3) to a maximum temperature of 400°F (204°C). Install the gear with the notch in the gear in alignment with the pin in the crankshaft. 3. Install shaft (1) in balance gear (2). Install the bolts in the shaft. Put the complete unit in position behind the camshaft gear as shown. Make sure the "V" mark on the two gears are in alignment with each other. Tighten the bolts that hold the balance gear in position. 4. Install plate (5) and the four bolts that hold the balance gear to the shaft. Make sure the groove in the plate is toward the gear.5. Push the camshaft toward the rear of the engine. Install thrust plate (4) and the bolts that hold the camshaft in position. Make sure the "V" mark on the camshaft gear is in alignment with the "V" mark on the balance gear.6. Remove tooling (C) (the two bolts) from the rear balance weight gear. Turn the engine with tool (B) to install the four bolts that hold the rear balance weight gear to the camshaft.7. Install the two studs in the flywheel housing.8. Install the turbocharger return tube assembly.end by:a) install timing gear cover

Have questions with 101402-4160?





Group cross 101402-4160 ZEXEL

Isuzu 

9 400 613 890 
8970208820 
INJECTION-PUMP ASSEMBLY
4BD1-PTY
9 400 613 891 
8943879120 
INJECTION-PUMP ASSEMBLY
4BD1
 
8970262850 
INJECTION-PUMP ASSEMBLY
4BD1-PTY
 
8970262851 
INJECTION-PUMP ASSEMBLY
4BD1-PTA
9 400 613 892 
8970262852 
INJECTION-PUMP ASSEMBLY
4BD1-T
 
8970209290 
INJECTION-PUMP ASSEMBLY
4BD1-T
 
8970209291 
INJECTION-PUMP ASSEMBLY
4BD1-T
 
8970209292 
INJECTION-PUMP ASSEMBLY
4BD1-T
 
8970209293 
INJECTION-PUMP ASSEMBLY
4BD1-T
9 400 613 893 
8970209294 
INJECTION-PUMP ASSEMBLY
4BD1-T
 
8970261360 
INJECTION-PUMP ASSEMBLY
4BD1
 
8970261361 
INJECTION-PUMP ASSEMBLY
4BD1
 
8970261362 
INJECTION-PUMP ASSEMBLY
4BD1
 
8970261363 
INJECTION-PUMP ASSEMBLY
4BD1
9 400 613 894 
8970261364 
INJECTION-PUMP ASSEMBLY
4BD1
F 019 Z10 324 
8970314860 
INJECTION-PUMP ASSEMBLY
4BD1-T
F 019 Z10 325 
8970314861 
INJECTION-PUMP ASSEMBLY
4BD1-T
F 019 Z10 326 
8970314862 
INJECTION-PUMP ASSEMBLY
4BD1-T
F 019 Z10 327 
 
INJECTION-PUMP ASSEMBLY

Isuzu 

9 400 613 895 
8970314863 
INJECTION-PUMP ASSEMBLY
4BD1-T
101402-4160  

101402-4161 
 
8970200410 
INJECTION-PUMP ASSEMBLY
4BG1
 
8970200411 
INJECTION-PUMP ASSEMBLY
4BG1
 
8970431270 
INJECTION-PUMP ASSEMBLY
4BD1PTA
9 400 613 896 
8970431271 
INJECTION-PUMP ASSEMBLY
4BD1PTA
F 019 Z10 573 
 
INJECTION-PUMP ASSEMBLY

Isuzu 

9 400 613 897 
8970461831 
INJECTION-PUMP ASSEMBLY
4BD1
9 400 613 898 
8970431980 
INJECTION-PUMP ASSEMBLY
4BD1
Back to top